Aerial view of the Edmonton Incinerator under construction.
Construction of the energy recovery facility at Edmonton Eco Park. Photo: NLWA.

The cost of a long-delayed new incinerator in north London will balloon to £1.25bn, after councillors agreed new terms with contractor Acciona at a quarterly meeting held at Camden Town Hall this month.

The 14 councillors sitting on the North London Waste Authority (NLWA) has raised the cap from £885mn to £1.25bn and renegotiated the completion date to December 2029 — two years beyond what was initially planned.

The NLWA is responsible for disposing of waste from around two million residents across seven boroughs: Enfield, Haringey, Barnet, Camden, Hackney, Islington and Waltham Forest.

£700mn has already been spent on the energy recovery facility (ERF) in the Edmonton Eco Park, which was approved in 2017 and began construction in 2022, earning scrutiny from campaigners and councillors.

Groups such as Stop the Edmonton Incinerator Now (StEIN) have expressed concerns it could increase demand for waste across the area and release harmful particles into the air, despite reassurances from the NLWA.

Earlier this month, the Greens said in a joint statement they backed the new incinerator despite years of opposition, after “inheriting a poisoned chalice”.

NLWA chief Councillor Jacob Cable said this week: “At this late stage in construction and taking all the facts into consideration, we have come to the decision that it is in the public interest for the facility to be finished and for the new terms to be agreed.

“Cancelling the project at this stage would impose significantly greater costs on the boroughs.”

Cllr Cable added: “Members have ensured that the new agreement is robust and binding, with the contractor fully accountable for the delivery and commissioning of the facility. This has been reinforced by in-depth reviews carried out by independent expert advisers as well as auditing of Acciona’s performance, which has led to increased governance and oversight.

“Most importantly, the incinerator will be publicly owned and income earned from the generation of energy will continue to help reduce costs for council taxpayers. There will never be a situation in north London where our boroughs are locked into a contract with a private provider which forces us to supply waste for burning.”

The authority says there has been a significant improvement in productivity recently, with more than 400 skilled workers on site every day compared to 200 at the beginning of this year.

Once the facility is finished, the cost per resident will be about £1.50 per week. That levy will cover rubbish collections, recycling, and the operation of eight recycling centres across north London.

If it was to be cancelled, the NLWA says it would have cost the boroughs an additional £100mn a year by 2030/31.

This would have included repayments on existing loans, paying private operators to either incinerate or put the rubbish in landfill elsewhere. It would have also meant about 30,000 extra lorry journeys undertaken each year to transport rubbish to those sites.

Cllr Cable said that he had recently written to request funding support for emerging green technologies.

“Following our decision to complete the ERF, NLWA members will be pushing for significant systemic change to ensure that unsustainable waste and rubbish are reduced as much as possible,” he said.

“This includes ensuring that far less plastic ends up being incinerated. We call on this government to act and urgently ban more unnecessary, tricky-to-recycle plastic.”

North London Waste Authority, Thursday 12 November 2026, Council Chamber, Camden Town Hall. Agenda and reports.